High court Judgement on G.O.37 date 18-02-2005

Rahmanpuram Gram Panchayat & Others
v./s
The Government of Andhra Pradesh, Rep. by its Secretary, Panchayat Raj Department, Hyderabad & Others

(High Court Of Telangana)


Writ Petition No. 4311, 4321, 4343, 4348, 4372 & 4540 Of 2010 | 07-06-2010

These six writ petitions can be conveniently disposed of by a common order as all the writ petitions are filed by Village Gram Panchayats represented by Sarpanches aggrieved by the action of the respondents in not entrusting the construction of Watershed to the Village Habitation Works Committee (VHWC) constituted by the respective Gram Panchayats in accordance with G.O.Ms.No.37, Panchayat Raj & Rural Development (PROGS.IA) Department, dated 18.02.2005, and G.O.Ms.No.10, dated 10.01.2006.

It is the contention of the petitioners that all the works under Food for Work Programme (FWP) with or without rice component whose value is less than Rs.5,00,000/- are ought to be entrusted to VHWC and the watershed construction/maintenance works are also ought to be entrusted to the Gram Panchayats. They relied on the two Government Orders referred to hereinabove and also a judgment of this Court in Pallamalli Gram Panchayat, Pallampalli Village v Government of Andhra Pradesh (2008 (5) ALD 246) in support of the contention. Respondents who filed counter affidavit of respondent No.3 opposed the writ petition. Their grievance is that the construction/maintenance of Watershed is a programme fully/partly funded by the Central Government, that the project of Watershed in identified places has to be carried out in accordance with the Common Guidelines for Watershed Development Projects, 2008 (hereinafter referred to as, Guidelines), issued by the Government of India and that as per these Guidelines the Gram Panchayats have a limited role of supervising the works and they cannot be entrusted with the construction of the watershed projects. After giving due consideration to rival submissions and examining them in the light of the Guidelines, this Court is of considered opinion that these writ petitions should be dismissed for the reasons that follow.

The purpose and purport of G.O.Ms.No.37 has been elucidated in Pallamalli Gram Panchayat (supra). Instead of again redoing exercise, for the sake of convenience, paragraphs 7 and 8 from the said judgment may be adopted herein also.

The Engineer-in-chief (E-in-C), Panchayat Raj, Hyderabad, addressed a letter No.T1/18233/75, dated 12.01.2005, to the Government informing that the contractors/middlemen avoided the execution of works, which are tied up with rice component. He, therefore, requested that such works need to be grounded and completed immediately by entrusting to the local bodies/user groups instead of following normal procedures like tender procedures, which are likely to take time and allows the contractors/middlemen. He also requested for permission to entrust the works like cement roads and other works taken up with rice component costing up to Rs.10,00,000/- by entrusting the same to user groups. By the time E-in-C addressed the letter to Government, the Government had initiated several rules tendering for public works with a view to bring in simplification of procedures, great transparency and better quality of works. The Government were also aware of various guidelines laid down by them with regard to Food for Work (FFW) programme as well as the works taken up under different programmes like Sampoorna Grameen Rozgar Yojana (SGRY). With this experience in the background, the Government contemplated to generate employment of the villages giving opportunity to the local people through the committees to plan, execute and monitor the works as per the budget allocations to the villages in order to ensure better quality in execution and subsequent maintenance. This was done as disclosed in G.O.Ms.No.37 dated 18.02.2005 itself, as a precurse to decision of Government in devolution of powers to the Panchayat Raj institution.

Contd.Page.2
Pages: 1 2 3


4 comments:

  1. Hi there, I read your blogs on a regular basis. Your humoristic style is witty, keep it up! Thank You for Providing Such a Unique and valuable information, If you are looking for the best DA Cost Estimates, then visit AussieQS. I enjoyed this blog post.

    ReplyDelete
  2. Good Evening Sir.
    I want to know the procedure to take up civil works such as construction of CC Roads, drains etc., who will execute the works at GP with GP Funds? Please share the GOs and Circulars

    ReplyDelete

Featured Post

Fixation of Mutation Fee in Gram Panchayats in the State

GOVERNMENT OF TELANGANA ABSTRACT Panchayat Raj & Rural Development Department – Mutation Fee – Fixation of Mutation Fee ...

Popular Posts